Preparatory Work for An Underwater Concrete Floor: Tsurumi Pump Used As Sediment Hoover

11.11.2020
Cement suspension, sand, mud and pebbles in the water: During the construction of a rainwater retention basin in Bielefeld, Germany, the "hoover of the construction diver" helps to install the underwater concrete floor.
Preparatory Work for An Underwater Concrete Floor: Tsurumi Pump Used As Sediment Hoover

The specialists prepare the "hoover of the construction diver" for use. Clearly visible is the self-created connection of the suction trunk. In the background the still clean hose outlet. (Image source: Tsurumi (Europe) GmbH)

The higher the property prices, the denser the building development. This has consequences for the urban infrastructure. Bielefeld is also confronted with the flip side of the building boom, as the increasing sealing of the ground makes it more difficult for rainwater to drain. The most recent project of the environmental authorities is an underground rainwater retention basin with a capacity of 10,000 m³.

Anchors in the ground
For this purpose, a 20-metre deep, surrounding bored pile wall was first set. The lower end is formed by the installation of a 110 cm thick concrete base with 2,500 m³ of concrete.

The target excavation level lies in the aquifer. In order to prevent the concrete base from being driven up or broken by the groundwater pressure, anchors were inserted 20 metres deep into the ground in a 3 x 3 metre grid. Hardly avoidable: During the grouting of the threaded steel elements, excess cement reaches the bottom of the excavation, where it mixes with drilling and ultra-fine slurries.

"You can't concrete an excavation pit that contains sludge," explains Marcel Meyer from the commissioned specialist Bautauchen & Wasserbau Sauerland GmbH from Brilon. This leads to leaks at the wall connections. "The concrete roller presses the sludge against the walls, later the ground water rises and floods the pit". In order to prevent the hydraulic ground failure, the sludge deposits, semi-hard and hard cement suspensions must be removed over the entire area.

Pump most important tool
The hard elements are recovered individually by divers and brought out of the pit in skeleton boxes. For the (larger) rest, Meyer comes up with the "hoover of the construction diver": a powerful Tsurumi pump, which has been slightly modified. Instead of the open suction basket, there is a hose connection at the inlet: with the suction nozzle at the other end, the divers bring up the loose floor covering from a depth of four metres. In sedimentation tanks the mixture calms down and the solids sink down. This means that the return water is largely free of sediment and sludge and can be returned to the pit.

A bone job for the divers that work in group rotation: "All manual dismantling work," emphasises Meyer. Good experience has already been gained with the Japanese pumps. They have even proved themselves with water containing bentonite. There is not much choice on the market, says Meyer, because pumps for this work not only have to withstand the difficult medium, but also have to have a long service life. While the concrete floor is scheduled to be constructed for around 30 hours at a stretch, two and a half months are estimated just for the preparatory suction work. The divers manage 9 to 10 hours a day.

Over 4 cubic metres per minute
The pump used, a GPN 415, is a medium-sized unit from the Düsseldorf-based manufacturer. It achieves a delivery rate of 4110 l/min and a maximum delivery head of 21,5 metres. It is remarkable that an agitator pump is used here to remove granular material up to 30 mm in diameter from the excavation pit with apparent ease. The manufacturer has done some preliminary work in the design for this. For example, the GPN is equipped with a double internal mechanical seal without contact with the abrasive pumping medium. Furthermore, a shaft sleeve with a sealing ring and several sealing lips protects the shaft from the entrained cement particles. Many components such as the impeller and wear plate are made of hardened materials, including extremely hard silicon carbide used for the shaft seal. The fact that the pump is optimally lubricated in every position is thanks to Tsurumi's oil lifter, an in-house development. Divers do not have to worry about the issue of tightness either, as the manufacturer hermetically encapsulates each individual electrical conductor in a composite mass.

More articles on this topic

Tsurumi Launches Improved KRD Series

21.08.2024 -

Tsurumi, one of the major manufacturers of dewatering and sewage pumps, is replacing one of its best-selling series. The reason for this is a significant increase in performance: The heavy-duty dewatering pumps for sand and slurry, previously known as KRS2, have been extensively upgraded and are now known as KRD.

Read more

Tsurumi Celebrates its 100th Anniversary in the Year of the Dragon

26.01.2024 -

Dewatering and sewage pumps are the world of manufacturer Tsurumi, which is celebrating its centenary in 2024. Over 500 models up to 30 m³/min or 216 m delivery head are listed in the catalogue for Europe alone. Worldwide, the manufacturer even offers over 1800 models with motor outputs of up to 300 kW for all conceivable applications, including clear and salt water.

Read more