Voith Hydro Sets New Benchmarks with First Horizontal, Six-Nozzle Pelton Turbine at Gerlos 1 Power Plant

31.01.2023
The trial operation of the first horizontal, six-nozzle Pelton turbine at the Gerlos 1 power plant has been running successfully for over two months now, and is setting new benchmarks.
Voith Hydro Sets New Benchmarks with First Horizontal, Six-Nozzle Pelton Turbine at Gerlos 1 Power Plant

Special transport of the 6.5m wide turbine housing from St. Poelten to the Ziller Valley in Tyrol. (Image source: Voith Hydro)

In the Pelton turbine, which is especially suited to plants with high heads, the water is directed by forming free jets at very high velocity from one or several nozzles to the Pelton runner. Until now, Pelton turbines with more than three nozzles have always been designed with a vertical shaft. The main reason for this was that it allowed higher efficiency than a horizontal arrangement. Voith Hydro has now successfully eliminated this drawback, as demonstrated in the Gerlos 1 power plant, where for the first time, an efficiency level comparable to that of the vertical configuration has been achieved. The plant’s existing four vertical Pelton turbines were successfully replaced by one six-nozzle horizontal Pelton wheel.

Applications
In addition to this application, the technology is of particular interest for upgrades of existing hydropower plants where single- or double-nozzle horizontal units are already installed. This is because the turbine can be replaced without major structural works, which significantly reduces civil costs and installation times. At the same time, there is enormous potential for increasing efficiency. The associated potential reduction in the number of turbines can likewise lower future maintenance costs. The new development is also a winning solution for new systems, as it requires less excavation and is more compact with a smaller footprint than conventional solutions. This is also associated with a shorter installation time, which substantially reduces the overall investment costs.

Ongoing development work
The interaction between the water jet and the buckets of the Pelton wheel is extremely short, often just a few milliseconds. This is why the flow simulation of Pelton turbines is by far the most complex and difficult of all hydraulic turbomachinery simulations. Voith Hydro has refined the methods in recent years such that the housing flow can now also be analyzed. This important advance also made a significant contribution to the development of the new concept.

Since the beginning of the 20th century, Voith Hydro has supplied thousands of Pelton turbines in a wide range of sizes and outputs all over the world. For many years now, the company in Germany has been conducting intensive research on the concept of multi-nozzle, horizontal Pelton units. The resulting developments of all horizontal Pelton turbines with more than three nozzles are grouped under the designation “HP3+”.

Last year, Voith Hydro experts presented the technology at a leading hydropower conference in Vienna. This world premiere was preceded by extensive tests and pilot programs at the company’s own R&D center in Heidenheim. The first customers, including Austrian utility Verbund, are already using the innovative design.

Impressive transport operation
Even before the new unit was commissioned, the spectacular transport operation for the turbine housing was already causing a stir. At the beginning of April 2022, this 54-ton giant left the grounds of the Voith Hydro plant in St. Poelten, Austria. Apart from its weight, the dimensions of the unit were also impressive: just under nine meters long, more than six meters wide and over four meters high. This logistical masterstroke could be accomplished by means of a heavy transport operation taking an entire three nights.

More articles on this topic

ANDRITZ to Equip New Hydropower Plant in Turkey

12.06.2024 -

The Turkish water authority Devlet Su İşleri (DSI) has selected international technology group ANDRITZ to supply the electro-mechanical equipment for the new 160 MW Silvan hydropower plant in Türkiye. The company will supply four 40 MW turbines, four generators, associated hydropower plant equipment, and a 154 kV switchyard system.

Read more

Voith Equips 2 GW Hydropower Plant in Angola

22.12.2023 -

Technology group Voith is set to supply equipment for the large-scale hydropower plant Caculo Cabaça in Angola, West Africa. The order comprises all electrical and mechanical equipment, including the installation of four Francis turbines with an output of 530 MW each, an additional Francis turbine with an output of 52 MW, generators, control and auxiliary systems and a customized training concept.

Read more