ANDRITZ to Rehabilitate the Hydraulic Passages at Canadian Generating Station
Carillon Hydroelectric Power Plant on the Ottawa River, Canada (Image source: Hydro-Québec)
This order follows the recent contract from Hydro-Québec for the first phase to complete the re-equipment of six 54-MW turbine/generator units of this plant. Realization of this additional project will span over seven years.
The first part of the contract comprises all work related to the design, manufacture and installation of hydro-mechanical equipment required for the repair and / or replacement of six hydraulic passages (including civil mechanical work), 18 new intake gates (6 m x 10 m), 18 sets of new embedded guides (25 m), rehabilitation of 18 trash racks (6 m x 20 m), as well as 18 new hydraulic hoist systems.
Source: ANDRITZ AG