The Putzmeister P 715 Piston Pump Provides Technical First Aid

20.03.2015

Spectacular stabilisation of a hillside in the Wutach Valley, southern Black Forest.

The Putzmeister P 715 Piston Pump Provides Technical First Aid

The magnitude of the landslide can only be fully appreciated by standing directly at the top of the slope and looking down towards the L 171. (Image: Putzmeister)

Easter 2014 will be engraved in the memory of the residents of the Black Forest community of Wutach for many years to come: on Easter Sunday between 6 and 7 p.m. the first of many mighty fir trees crashed down onto the L 171 country road, triggering a landslide of massive proportions. The lifeline to the village of Ewattingen and connecting road to the district of Donaueschingen remained blocked for several months until provisional stabilisation of the hillside in the summer of 2014 allowed the road to partially open.

Several observant citizens of Ewattingen informed Hartmut Trenz, road construction expert for the regional council of Freiburg, as early as March that an increasing number of stones were falling onto the road at a specific point and so the hillside was inspected and surveyed by qualified personnel from a wide range of fields. After a huge crack had opened up in the hillside within a few days, on Maundy Thursday the L 171 between Ewattingen and the Wutach mill was closed for safety reasons. A wise decision considering what happened only three days later. Several firs on a steep southern slope above the busy L 171 were no longer able to hold onto the slope and masses of earth, boulders and debris followed the trees down the hillside.

Immediate measures included removal of the fallen pines and boulders from the road as well as the felling of other trees that were in danger of falling in the landslide zone. A special company from Würzburg was commissioned to remove approx. 1,200 m3 of excess earth from the geologically unstable zone using a walking excavator.

For weeks, the community of Ewattingen was just a white dot on the map.

Following further geological studies, a decision was made to strengthen the hillside above the road using shotcrete and anchoring equipment, and the company Bombardi Tiefbau from Titisee-Neustadt was commissioned to stabilise the problematic hillside.

After approx. 120 metal anchors were inserted, a shotcrete wall was sprayed across the entire width of the hillside to stabilise it. Most of the time, the experts were only able to work from a suspended cage during this challenging job and as always, had to deliver quality results under extreme conditions. A Putzmeister P 715 piston pump provdied the experts from Bombardi with assistance: equipped with an automatic dosage system for set accelerating admixture and a 60 metre long DN 50 hose, the hydraulic piston pump demonstrated a perfect combination of powerful technology from large pumps with an extremely compact and user-friendly design as well as the ease with which pumpable material with a grain size of 8 mm can be conveyed. The T-chassis made it easy to transport the machine to the construction site and manoeuvre it to the top of the slope. Specially designed for construction sites and continuous use, the state-of-the-art P 715 pumped a total of 1,000 m³ of material onto the unstable hillside.

Motorists have enjoyed partial "free passage" along the L 171 since July 2014.

After a special fence for stopping sliding debris was erected and a net for preventing new landslides was installed, one lane of the L 171 was cleared again for traffic after having been closed for several months, albeit with a temporary traffic light control. Geologists are continuing to monitor the hillside because the unstable ground in the area around the Wutach gorge is expected to spring some rather unpleasant surprises in the future. Hartmut Trenz, road construction expert and site manager for the landslide in the Wutach Valley, explained that it will almost certainly not be the last landslide witnessed by the residents of Ewattingen and it is important now to reforest the area around the landslip to provide additional stability.

More articles on this topic

Ebara Elliott Energy Receives Order for AMIRAL Project in Saudi Arabia

13.12.2024 -

Ebara Elliott Energy (EEE) has been selected to supply advanced equipment for SATORP’s Strategic Expansion (AMIRAL) petrochemical complex, located in Jubail on Saudi Arabia’s eastern coast. The contracts for the project were awarded by Hyundai Engineering Company and Maire Tecnimont, further cementing EEE’s role as a trusted partner in critical infrastructure projects in the region.

Read more

SIMFLO and SitePro Bring Industry-Changing Technology to New Pump Testing Facility

05.12.2024 -

Lubbock-based SIMFLO, one of the nation’s providers of industrial, municipal, and commercial and agricultural-use pumps, has added industry-changing, first-of-its-kind innovative technology to its new Engineered Products Facility, which features one of the largest and most advanced vertical turbine test facilities in North America. The technology, provided by Lubbock-based SitePro, Inc., allows SIMFLO to enable remote witness testing from anywhere in the world, thus saving customers and engineering firms significant time, expense, and resources.

Read more

Seawater Lift Pumps Delivered in Record Time

04.12.2024 -

In the competitive world of supplying equipment to offshore platforms, Sulzer has succeeded in delivering another contract for seawater lift and water injection pumps. Streamlined processes have enabled the delivery time to be cut by almost 25% compared to industry expectations, saving precious project time and securing important contracts for two manufacturing sites.

Read more