Armstrong Streamlines Boiler System Upgrade for RWE Generation UK
Armstrong Industrial delivered a turnkey replacement system comprising three 130 kW skid-mounted boilers, individual boiler pumps and an integrated control panel (Image source: Armstrong Fluid Technology – S. A. Armstrong Limited)
RWE Generation UK had identified the need to replace an ageing gas pre-heating system at its Cheshire site. The existing installation comprised three ageing boilers and outdated controls, creating operational and reliability challenges. The replacement project had to be completed during a tightly controlled five-day shutdown, making project planning and coordination critical, according to Ian Parkinson, Offering Manager – Gas at Armstrong Industrial. This constraint meant that the project had to be engineered around the shutdown from the outset.
“When a critical system can only be taken offline for a matter of days, the shutdown window effectively becomes the project’s most important constraint,” said Parkinson. “The more work that can be completed, tested and integrated before equipment reaches site, the less installation activity has to take place while the facility is offline.”
Off-Site Fabrication
Armstrong Industrial delivered a turnkey replacement system comprising three 130 kW skid-mounted boilers, individual boiler pumps and an integrated control panel. The system was fabricated off-site and fully tested before being delivered to the Cheshire facility.
“This approach shifted a significant proportion of the assembly and integration work away from the critical shutdown period,” he explained.
Once on site, Armstrong Industrial removed the redundant equipment, installed the new boilers and control system within the existing plant room, and completed the necessary tie-ins to existing connections.
Controlling Quality and Time
“Off-site fabrication gives the project team greater control over both quality and programme,” said Parkinson. “Instead of carrying out every stage of assembly and integration in a live industrial environment, the packaged system can arrive on site substantially prepared for installation.”
This can simplify the work, he noted, which in turn reduces uncertainty and makes better use of the limited shutdown time. It was important that the upgraded boiler system could demonstrate its operational readiness immediately after installation, said Paul Doyle, Cheshire Site Manager at RWE Generation UK.
“We are extremely pleased with the on-schedule project delivery,” said Doyle. “The new boiler system performed flawlessly for two separate full load dispatches from National Grid over the weekend.”
Parkinson emphasised that the project illustrated a wider principle for operators planning upgrades to critical infrastructure.
“Modernisation is not simply a question of replacing old equipment with new equipment,” he said. “The engineering strategy has to take account of how the facility operates, when systems can be taken offline and what is required to return them to service safely and reliably.”
This means that planning, prefabrication, integration and commissioning all need to form part of the same delivery strategy, he said.
Operational Readiness
RWE’s experience also highlighted the value of defining operational readiness as a key project outcome rather than treating installation as the finish line. By commissioning and testing the new system before it was required to support full operational load, Armstrong Industrial verified that the upgraded infrastructure was ready for operation.
The project was delivered on a fixed-price basis, providing cost certainty alongside the programme certainty required for the five-day shutdown. Addressing the Armstrong Industrial team, Doyle added: “It is fair to say you are one of the best contractors I have dealt with in 20 years in the power industry.”
Armstrong Industrial has since been commissioned to supply another two boilers at this site; according to Parkinson, this contract has also been completed.